|
(Note: This Monograph has been reproduced
by kind permission of the Commission for the New Towns now known as English
Partnerships. It is published for general interest and research purposes
only and may not be reproduced for other purposes except with the permission
of English Partnerships who now hold the copyright of LDDC publications)
Top of Page
Foreword
Docklands in 1981 presented a rare opportunity for engineers
to display their full array of skills on a unique scale within a major
urban conurbation. More than any other part of London, Docklands required
the provision of extensive and major infrastructure on a massive scale
- the expansion of basic utilities such as gas, water, electricity, the
provision of drainage both surface and foul, as well as the construction
of new roads and tunnels and rail and other transport networks.
Apart from new provision and investment, the condition
of existing structures both on and below the ground had to be assessed
including marine structures such as dock and river walls, lock gates and
related infrastructure. All this as well as other elements had to be extensively
surveyed before decisions could be made on what to renovate, repair or
replace before the task of regeneration could commence.
In looking back it can be seen that London Docklands
in 1981 was an untested market and much of the engineering design work
had to be made in advance of known development requirements or private
sector responses. Such circumstances posed a number of engineering challenges
particularly in the early phases of the overall regeneration programme.
This monograph, one in a series published by the Corporation
in its final year of operation, outlines how the Corporation's engineers
together with their consultants contributed to the regeneration and physical
transformation of London Docklands.
LDDC
March 1998
Top of Page
Top of Chapter
Introduction
"At the beginning of 1981 London's
Docklands bore the scars of 20 years of decline and neglect. Dock closures
commencing in 1967 had led to the disappearance of related industries.
New industry did not take the place of the old and 10,000 jobs were lost
in the three years between 1978 and 1981. A shrinking and increasingly
elderly population found itself isolated among wide tracks of derelict
land and buildings.
"Conventional local government solutions failed to halt the accelerating
decline. A new approach was needed. The London Docklands Development Corporation
was created in July 1981 and charged with the regeneration of the area."
These words were written in 1986 by Nicholas Ridley,
the then Secretary of State for the Environment in an article for "The
New Civil Engineer" and they sum up exactly the situation which engineers
and project managers found when work started in London Docklands in 1981.
As
a result of the Corporation's initial investigations, a comprehensive
programme of land acquisition, land reclamation, infrastructure provision,
community support and marketing was put in place. This publication solely
addresses the provision of infrastructure along with land reclamation
programmes. Other issues are discussed elsewhere.
Part of the raison d'etre for establishing Urban Development
Corporations (UDCS) and the London Docklands Development Corporation (LDDC)
in particular was that the finance to support the infrastructure and land
reclamation programmes on the required scale could only be funded by a
Government agency using public money. it would have been impossible for
any one developer or a consortia of developers to have funded the infrastructure
and land reclamation programmes and justified economically the subsequent
development.
Other programmes were also put in place, for it was seen
as vital to provide not only the required infrastructure, but to enhance
all aspects of the environment. The result of this was that certain buildings
were listed and renovated. The fabric of churches e.g. the Nicholas Hawksmoor
churches, St George in the East and St Anne's Limehouse, were restored
and parks were created, together with community programmes.
The scene was therefore set. The Corporation would fund
and provide the infrastructure and land reclamation and the private sector
would provide and finance the developments.
The Corporation, early in its life, took the decision
to employ in-house consultants to assist the chief officers and permanent
staff in delivering its programmes. In the field of engineering and project
management in 1981 there was initially only one permanent engineer.
The contract for managing the Corporation's Project Programme
was awarded to W.A. Fairhurst & Partners, through competitive tender,
who were employed in June 1982 and have retained the contract to March
1998. W.A. Fairhurst & Partners also provided many of the professional
engineering staff. The in-house Quantity Surveyor consultants from 1982
to 1984 were Gardiner & Theobald. In 1984 following a competitive
tender process McBains Cooper vvere appointed and likewise retained the
contract until March 1998.
This structure was strengthened in 1990 when Bechtel
International were appointed for a three year period to assist in the
management, with W.A. Fairhurst & Partners, of major engineering projects
under construction at the time, including the Limehouse Link Tunnel, the
East India Dock Link Tunnel, the Lower Lea Crossing and work to Aspen
Way, together with a major tunnel sewer project.
During its lifetime the Corporation has spent £2.3 billion
on regeneration of which £1.86 billion was in Government grant and the
remainder from property sales. Of this more than 50% was the responsibility
of the Engineering and Project Management teams.
Top of Page
Top of Chapter
Provision of Services
Of all the tasks facing the Corporation at the outset
in July 1981, the provision of services was one of the most difficult.
What level of development would they have to support? No one knew, indeed
the whole venture was speculative. A development corporation on the scale
of London Docklands had not been tried anywhere in the world and therefore
had no precedent to give a guide.
Further, it was clear that the provision of services
and other infrastructure would have to take place concurrently with development,
this was especially true in Wapping and the Isle of Dogs, the latter of
which housed the Enterprise Zone, for ten years from 26th April 1982.
To have provided the infrastructure first in these areas would have taken
several years and the whole momentum, which was vital if this venture
was to prove a success, would have been lost. Simply the problem was,
what would be required? What capacity of services would be required and
what were the logistics of providing them 'cheek by jowl' with development.
However, in spite of there being no precedent, development
frameworks were produced by the Corporation's planners in which assumptions
were made about the type and density of development. Based upon these
assumptions the services i.e. drainage, water supply, power and communications
were sized. In the case of the Royal Docks and Southwark the capacity
of these planned services were sufficient for the subsequent and planned
development.
In 1984 it was thought that up to 8 million sq.ft (743,000
sq.m.) would be accommodated on the Isle of Dogs, attracted by the financial
incentives and relaxed planning regime of the Enterprise Zone. However,
by 1986 the LDDC had agreed in principle the proposed Canary Wharf development
of some 12 million sq.ft. (1.1 million sq.m.). A complete rethink regarding
the capacity of the services was required. By this time five years from
the start of the LDDC some of these services had already been installed.
Top of Page
Top of Chapter
Services in the Isle of Dogs -
Drainage
By the 1850's the lack of a proper drainage system for
London posed a serious health problem and diseases such as cholera had
become endemic. In the Summer of 1857 Parliament rose early, due to the
stench emanating from the river Thames and in 1858 the engineer, Joseph
Bazalgette, later to become Sir Joseph Bazalgette, was commissioned by
Parliament to design an effective drainage system for the whole of London.
Bazalgette's plan was to intercept the existing sewers,
which at that time discharged directly to the Thames, prior to their entry
into the river. These new sewers would drain by gravity to pumping stations,
which in turn would pump them up to a high level sewer known as the Northern
Outfall Sewer, which itself drained by gravity to Beckton. The site at
Beckton was chosen because foul drainage discharged at that point would
not be carried on the tide up as far as London. Since that time Beckton
has become the home of a major treatment works and now only clean water
is discharged into the Thames. The system designed by Bazalgette was based
upon a combined system with both foul and surface water discharging into
common sewers. In times of storm this system has the distinct disadvantage
that if flooding ensued then an element of the flood water would be made
of foul sewage. However, to prevent flooding as far as possible, the system
has an in-built safeguard which either allowed for the overflow to discharge
via weirs to the Thames or a pumped overflow to the River, neither of
which is an ideal solution.
Figure 1 shows
the strategic drainage system which had in the main been in existence
since the 1860s.
Top of Page
Top of Chapter
In the early 1980s the Corporation commissioned a study
of the capacity of the existing system, set against the development predictions
at that time. This was prior to the advent of Canary Wharf.
Due to the development predictions for the Isle of Dogs
it became clear that the capacity of the existing system would be exceeded
by both foul and surface water discharges - the foul, due principally
to the increase in residential development, and the surface water, due
to the construction of highways and hard standing such as car parking
areas and so on.
Following this study two options emerged, the first and
the one which was eventually constructed was to enhance the drainage to
the Isle of Dogs and take it north to Abbey Mills, via the new Northern
Drainage Scheme Phase 2, as shown on Figure
2. From Abbey Mills it would be pumped into the Northern
Outfall sewer and thus discharged at the Beckton Treatment Station.
The second, and more imaginative scheme, was once more
to enhance the drainage of the Isle of Dogs, but to pump across the River
Lea and discharge it into the then planned drainage at the south west
corner of the Royal Victoria Dock. It would have then been routed to the
planned North Woolwich (Store Road) Pumping Station from where it would
be pumped to Beckton. However, due to the development forecasts at that
time it was not considered economic. However, with the coming of Canary
Wharf, it quickly became obvious that this scheme would have had distinct
advantages. By the time Northern Drainage Phase 2 was constructed in 1990,
it was too late to pursue the second option, since the Royal Docks station
which had been installed did not have the capacity to take this extra
flow.
Top of Page
Top of Chapter
The strategy for the first option was to incorporate
the enhanced drainage system into the existing system and where possible
separate the foul and surface water discharges. The discharge of as much
surface water as is possible to the Thames is important in terms of energy
saving in that it obviates the need to drain it from the Isle of Dogs
to Beckton, a distance of some 5 miles (10 km), and then treat it. To
implement the building of this system required the construction of two
Pumping Stations, one at Stewart Street on the Isle of Dogs and the other
at Abbey Mills.
The
Stewart Street Pumping Station designed by Sir William Halcrow & Partners,
with John Outram architects, was built by Peter Birse Ltd while the Abbey
Mills pumping station was designed by Halcrow and built by Miller Civil
Engineering. Halcrow were the principal consultants for Northern Drainage
while the main contractors were Millers and Lilley Construction.
The Stewart Street pumping station pumps the surface
water from the eastern trunk sewer in Marsh Wall and, in times of storm,
it pumps the excess combined flows to the river. In normal circumstances
all flows are collected in a "mega manhole" in the centre of
Prestons Road Roundabout from where they flow northwards to Abbey Mills,
either in the old low level No. 1 Isle of Dogs branch sewer built in 1860,
or the new Isle of Dogs low level No.1 sewer constructed in 1993.
To choose a route for this new major sewer presented
a difficult task. For safety reasons the building of the sewer required
the construction of 15 shafts, the positions of which in the main predetermined
the route of the sewer. The construction of many of the shafts resulted
in the diversion of services, changes to traffic flows and some inconvenience
to the local community. However, with careful planning, the co-operation
of the Police, and the local residents, the disruption was kept to a minimum.
The route itself commences adjacent to the manhole in Prestons Road, from
there it goes north crossing under the A102 north of the southern entrance
to Blackwall Tunnel, from there it proceeds northwards under Gillander
Street to the main construction shaft at Twelvetrees Crescent. From Twelvetrees
Crescent it proceeds northwards crossing under a main water course and
ring at Abbey Mills. The construction of the sewer took place at a lower
level than the existing low level No.1 sewer to take advantage of the
presence of London Clay, a material ideally suited to tunnelling.
Northern Drainage Phase II was a major infrastructure
project and the first addition to the existing foul drainage of London
built since the 1860s.
Top of Page
Top of Chapter
The construction of the tunnel employed the use of two
different types of tunnel lining, the section south of Twelvetrees Crescent
consisted of an expanding one pass lining, that is the rings are held
in place by the presence of a horizontal keystone, the placing of which
expands the other segments of the ring against the London Clay. The second
type of lining i.e. that north of Twelvetrees Crescent was constructed
at the interface of the London Clay and the Woolwich and Reading Beds,
a water bearing strata. This section of the tunnel was constructed under
an air pressure of 1 bar and employed the use of bolted segments which
were later relined.
Electricity
As with drainage the level of electric supply to the
island was insufficient for the forthcoming development. The first upgrading
to the existing system took place in 1984 and as a result a new 1 1 KV
transformer station was constructed at Simpsons Road in Poplar. This substation
took its 132 KV feed from the nearby Brunswick Power Station and the construction
of Aspen Way gave the opportunity to lay the feed cable with the road
construction, thus minimising disruption to the area. The second phase
of upgrading took place as a result of the Canary Wharf development. The
agreement between Olympia & York and the Corporation required the
Corporation to supply electrical power at 11 KV, and resulted in the construction
of an 11 KV substation at Ontario Way. This substation took its 132 KV
feed from the West Ham power station.
Top of Page
Top of Chapter
Gas
The gas distribution in 1981 for the Isle of Dogs was
based upon a low pressure system. With the predicted flows it was impossible
to satisfy the demand using a low pressure system. Since the existing
pipes could not sustain an upgrading to medium pressure these pipes had
to be replaced. Once more to minimise disruption, the installation of
new pipes was, where possible, undertaken together with works to the highways.
The main supply to the Isle of Dogs was taken from two
48" mains located in the A13 trunk road, but with the new demand
it was necessary to tap into the high pressure system on the east side
of the River Lea and to bring a feed across the river via a pressure reduction
station.
Telecommunications
The major provider of telecommunications was, and is,
British Telecom, however following privatisation other companies entered
the market including East London Telecommunications, Mercury and City
of London Telecommunications.
During the road building programme, the opportunity was
taken to lay banks of ducts, generally in the footpath. Each of the companies
were allocated dedicated banks of ducts and the opportunity was also taken
at this time to lay ducts for general traffic signalling throughout the
area. In deciding the number of layout of the ducts close co-operation
was undertaken with the various companies to satisfy their demand.
Ron Berry C.Eng., M.I. Struct. E.
LDDC Head of Engineering
(formerly W.A. Fairhurst & Partners)
Top of Page
Top of Chapter
Strategic Sewerage and Services in the Royal Docks
The Royal Docks are situated in the eastern part of the
LDDC's area and comprise the predominantly residential area of Beckton
in the north, and the former Port of London area - the docks - in the
south. The Royal Docks system formed by the Royal Victoria, Royal Albert
and King George V Docks is impressive, both in scale and its visual impact,
but despite these attributes, provided the greater challenge to sewerage
and servicing provision. These principal development areas are illustrated
on Figure 1 (151k) , together
with the details of the sewerage and services discussed in this section.
Development of the Beckton area commenced early on in
the life of the Corporation, carrying on work already started by the London
Borough of Newham. Development has been carried out on land formerly used
by Beckton Gasworks, along with allotments and existing waste ground.
Servicing of development sites by new sewerage and the other services
has been successfully achieved by the new provision and reinforcement
of existing services within, and at the boundaries of, the area. Sewerage
and services construction has followed a conventional approach with appropriate
measures taken in recognition of areas of contamination, consequential
on previous land use. Beckton (as at 1998) has capacity for further development,
and any additional services provision for the few remaining sites will
be generally met by connection to the existing network of sewers and utilities.
Top of Page
Top of Chapter
Services in the Royals
The LDDC's acquisition from the Port of London Authority
in the mid 1980s of the Royal Docks presented a challenge to sewerage
and services provision, principally due to the relative positions of the
dock water and adjacent land area. The principal feature of the docks
system, which subsequently dictated the configuration of the eventual
sewerage and services layout, is the vast impounded area of dock water
amounting to some 100 ha., surrounded by the quay side development area
of 140 ha.
The linear shape of the docks, which have a total length
of 4.5 km from the western to the eastern extremities with a depth of
dock water up to 9 metres, formed the main constraint which influenced
sewerage and services designs. The water areas bisect the development
land into the north and south side areas. The width of the dock waters
varies from 180 metres, to a much narrower width where the Royal Victoria
Dock and Royal Albert Dock meet at the Connaught Cut channel linking the
two docks. The Royal Albert Dock and King George V Dock to the east of
the Connaught Cut are separated by the London City Airport runway.
Alignments and the locations of the future sewerage and
services runs were also significantly influenced by the linear shape of
the development areas they were to service and by the barriers created
by the dock water.
The level of provision of sewerage and services was determined
initially with reference to the Corporation's Royal Docks development
framework, prepared in 1985, by the LDDC with the Richard Rogers Partnership.
The LDDC has laid foundations for the successful future
development of the Royals. Most of the infrastructure schemes have been
completed, a number of high profile developments have been agreed and
work on some of these schemes has started.
The development strategy proposed a variety of uses including
commercial, residential, office, retail and leisure facilities. In 1986
with more detailed information available, and with the emergence of major
development schemes in the Royals, the fundamental requirements to enable
design of sewerage and services were established. The volume and scope
of the proposed new development was much different than the existing land
use, as an area for handling cargoes and an enclosed dock system. Quay
side buildings, in this former use, included large warehouses and shipping
offices, grain silos and flour mills, together with railway yards. The
requirements and demand for sewerage and servicing needed to reflect the
different conditions which would prevail after redevelopment. The docks,
during their operational period, had been continuously redeveloped and,
as a consequence, the underground sewerage and services had been sequentially
adapted and modified to suit the changes. The process envisaged by the
Corporation was therefore not new, but would require fundamental review
of the existing sewerage and services infrastructure.
The run down of the docks during the 1970s and cessation
of shipping activity resulted in the Royal Docks area becoming derelict.
The combination of age and neglect of the buildings equally applied to
the sewerage and services which, as a consequence, could not give the
flexibility, the scope and the capacity to meet the requirements of the
regeneration proposals envisaged by the Corporation.
Top of Page
Top of Chapter
Sewerage and Drainage Network
The increase in services required for the proposed development
could not be accommodated by existing sewerage infrastructure feeding
out of the proposed new development area or services feeding into the
area. The existing infrastructure had not been designed to meet the increased
demands created by the planned increased volume of development. Much of
the existing sewerage outside the Royals, which could potentially drain
the new development and which was operated by the water authority, Thames
Water, did not have the capacity to provide for the existing development
and would need to be improved, irrespective of the redevelopment proposals.
The existing sewerage network and sewerage proposals were examined in
detail in conjunction with Thames Water prior to committing to design
and construction. A similar exercise was undertaken for services with
the other public utility authorities i.e. gas, electricity and so on.
As with the existing sewerage and drainage within the docks system, the
services infrastructure was formerly owned and operated by the PLA as
a private network and in general would not meet the specification and
standards of construction required by the statutory water and public utility
authorities.
Redevelopment on the scale envisaged, to a programme
determined to a great extent by market forces, would see a piecemeal provision
of sewerage and services infrastructure over time by individual developers,
unless a co-ordinated approach was adopted. The decision was taken by
the Corporation to provide main sewerage and services in a co-ordinated
manner as advance construction and as a means of enabling and encouraging
development in a pump priming exercise. The costs to developers of procuring
infrastructure in a piece-meal and less economic approach was thus obviated
and development sites would be able more or less to 'plug-in' to a 'ring-main'
arrangement. The 'ring-main' comprising the sewerage and services passes
through a substantial portion of the Royal Docks to enable the principal
sites to be serviced.
The fundamental requirements, which dictated the form
of the new sewerage, were determined by the decision not to allow discharge
of surface water run-off into the dock water, as had been allowed by the
PLA and by the increase in foul sewage discharges as a consequence of
the enlarged development. The separation of surface water and foul sewage
discharges by means of separate foul and surface water sewerage systems,
would enable less sewage to be pumped to and treated at the main Thames
Water sewage treatment works at Beckton and would therefore reduce costs
and place less burden on treatment capacity.
Surface water would be dealt with by discharge to the
River Thames, thus maintaining the quality of water in the Royal Docks
water area, being a large body of still water and not capable of being
recycled by flushing. In addition, the land area adjoining the dock water
lies at just above or below the impounded dock water level and cannot,
therefore, discharge by gravity into the dock water.
Top of Page
Top of Chapter
Pumping Stations
Two pumping stations have been built and are connected
independently to the foul and surface water sewerage systems. The Tidal
Basin Pumping Station, designed by Richard Rogers Partnership, is located
on the north-west of the Royal Victoria Dock and pumps surface water to
the River Thames via gravity mains and with a discharge capacity of 8
cubic metres per second. The station has been handed over to Thames Water
Utilities.
Foul water is pumped via the North Woolwich (Store Road)
Pumping Station, which is located in the south-east of the Royal Docks
area. This pumping station, designed by Nicholas Grimshaw & Partners,
was constructed under a joint venture between the Corporation and Thames
Water Utilities. The flow from the station is directed through rising
mains to the Thames Water Northern Outfall Sewer which then discharges
to the main Thames Water Treatment Works at Beckton. The North Woolwich
Pumping Station is more complex than the Tidal Basin Pumping Station in
that it has three separate and specific functions. The first is to pump
sewage flows from developments in the Royal Docks. The second is to pump
a redirected combined sewage flow, arising from the existing communities
to the south of the Royal Docks area - Silvertown and North Woolwich -
previously served by an old pumping station at Barge House Road and operated
by Thames Water. The third function is to deal with excess incoming flows
from the existing combined sewerage systems under storm surcharge conditions,
which discharge flows via storm overflow gravity mains to the River Thames.
The capacity of this station under normal operating conditions is 2.4
cubic metres per second and under storm surcharge conditions can pump
at the rate of 4.8 cubic metres per second discharging the excess flow
to the River Thames, via the gravity mains. Surface and foul water discharges
are conveyed to the two pumping stations via tunnels varying in size from
1.8 metres diameter to 2.4 metres diameter laid at depths down to 15 metres
below surface level. The total length of tunnels within the Royal Docks
connected to the pumping stations is 10 km with an additional 3 km of
trench constructed sewers forming the upstream and shallower lengths.
The alignments of this sewerage as far as practicable, have been selected
to maximise development areas so as to create flexibility in future development
layouts and to minimise encumbrance on building layouts.
The depths of the tunnels have been influenced by the
need to link the north and south side development areas below the dock
water bed and also to satisfy hydraulic requirements in relation to the
areas being drained and the distances to the pumping stations.
Tunnelling has been carried out using a range of tunnel
boring techniques, through a variety of different strata, including the
Flood Plain Gravels, Woolwich and Reading Beds, London Clay, Thanet Sands
and Chalk. Tunnels have been constructed by pipejack and segmental construction,
to suit the variability of ground conditions encountered. The tunnelling
was not without disruption and was affected in different ways. In one
case, siltstone at the base of the tunnel drive caused the buckling of
the tailskin of the tunnel boring machine and caused difficulty in maintaining
direction of the machine and line of the tunnel. The resulting effect
of this was to complete the work after some delay to progress. Considerable
additional cost was incurred and compressed air working, following the
removal of the damaged tailskin, was required.
Top of Page
Top of Chapter
On another drive, passing under the western end of the
London City Airport, the tunnel boring machine settled, causing a termination
of tunnelling at this location as the machine became lodged. The drainage
system, as a consequence of this problem, had to be redesigned and constructed
as an alternative alignment to meet the future drainage requirements for
development. The shell of the trapped machine remains buried with all
the removable internal parts taken out.
Despite some of the difficulties encountered, due mainly
to the variability of the ground conditions encountered, the Royal Docks
is now fully serviced with trunk sewerage facilities. Negotiations to
transfer the sewerage system to Thames Water Utilities are in hand and
it is anticipated that this will occur during 1998.
The principal consulting engineers involved in the design
of the sewerage and drainage network in the Royal Docks were Sir William
Halcrow & Partners and the London Borough of Newham. The major contractors
were Miller Civil Engineering, Nuttails, Streeters and Donelan.
Top of Page
Top of Chapter
Strategic Services
The strategic services comprise the public utilities
equipment, which include within the items provided, the trunk water and
gas mains and ductwork through which cabling may be drawn for electricity
supplies and telecommunication cables by the respective service providers.
These might include the regional electricity company and telephone/cable
companies. To service the Royal Docks area, the route of the services
generally follows the peripheries of the Royal Victoria Dock, Royal Albert
Dock/south of the King George V Dock area in the form of two circular
routes joined at the Connaught Crossing to create a figure of eight circuit,
combining at this intersection to create a maximum service provision and
flexibility of operation for the principal development sites. All the
services are kept together in a single corridor, where possible, to minimise
the impact of the corridor on developable areas. The general width of
services in the corridor is maintained at around 6 metres.
The water mains are connected to external supply mains
at the periphery of the area and are generally interconnected with two
way feeds to maintain security of supply. Gas mains are connected via
two gas governors, positioned at the east and west extremities of the
Royal Docks and are also linked to a Pressure Reduction Station at Connaught
Crossing. This station is fed by a high pressure primary main, bringing
gas from outside of the core area.
Telecommunication cables include British Telecom and
Cable & Wireless links, comprising a mixture of copper cables and
fibre optic. The development of fibre optic technology and increasing
adoption of its use has modified the requirement for ductwork laid in
the ground. The original proposals for supply in the late 1980s, demanded
upwards of 18 to 24 ducts for copper cable to be laid, in order to accommodate
the number of lines required for anticipated development. Future provision
of ductwork, where not yet provided, will reduce in quantity to reflect
the current technology of fibre optic cable connections.
As regards electricity supply, a base shortfall in primary
supply was identified at the planning stage in the late 1980s. This shortfall
was established on the level of development proposed and associated demand
for electricity.
Although there had been decline in riverfront industry,
only 30 megawatt (mw) surplus capacity could be made available from the
local substations to supply development in the core area. The shortfall
in supply, however, of 140mw had been identified at the planning stage,
which at that time would have involved a contribution by the Corporation
of £20 million to procure a supply via a new primary substation to be
located at the eastern end of the core area. This large cost would be
offset by rebates, thus reducing the large capital contribution. However,
the means of achieving the rebate depended on power consumption being
achieved within an agreed time frame. This method assumed development
to occur during a specific period following construction of the substation.
The risk of not achieving development within the prescribed time frame
meant that the Corporation would forego the rebates.
The decision was taken to defer the substation project
as a consequence of the downturn in development in the early 1990s, which
vindicated this action. However, although the level of development may
not, in the current development strategy, be quite as dense and consumptive
of power as perhaps considered previously, there will still be a requirement
to reinforce electricity supply for the development proposals.
The current approach to this problem is being pursued
via alternative energy solutions to manage demand on a more economic level.
Combined heat and power plants are being promoted together with an alternative
electricity provider.
The principal consulting engineers involved in the design
of strategic services in the Royal Docks were WSP Graham Development Ltd.
Major contractors were Nuttall, Peter Birse Ltd, May Gurney and Co. Ltd,
Cementation Construction Ltd and Norwest Hoist Construction Ltd.
John Barratt C.Eng., M.I.C.E.
Senior Engineer
W.A. Fairhurst & Partners
Top of Page
Top of Chapter
Geoenvironmental Issues
The correct awareness of geotechnical and environmental
issues has been a central factor in the development of Docklands. The
formation of the LDDC gave an opportunity to undertake a systematic appraisal
of the regional conditions to provide support to its redevelopment. The
centralised approach of regional appraisal contrasts to the usual situation
where such factors are restricted to specific and often relatively short
term aspects of each engineering project. The LDDC, aware of the importance
of a comprehensive understanding of the ground conditions within its area
included geotechnics and environmental engineering geology as a central
function within the renewal procedure and retained Dr A F Howland of A
F Howland Associates to advise on such matters.
Top of Page
Top of Chapter
The Geological Setting
The Docklands area lies on part of the flood plain of
the River Thames within the geological province of the London Basin.
The availability of some 5,500 borehole records collated
in the Docklands area allowed a revision of the local geology and in particular
demonstrated that the large structural dislocation of the Greenwich Fault
did not cross the area, as traditionally understood to be the case. The
principal geological units of the area are shown in
Table 1. These are gently folded so that subsequent erosion
has caused various of the units to be present in different parts of the
region (Figure 1).
Water well records show the Chalk is approximately 200
metres thick. It is a weak limestone characterised by a whiteness and
purity. It forms the main aquifer of the London Basin.
The Thanet Sand is the oldest of the sediments which
infill the London Basin. It lies unconformably on the Chalk and in Docklands
is about 16 metres thick. In an unweathered state the Thanet Sand has
a noticeable green colour, due to the presence of the mineral glauconite,
but on weathering changes to a pale yellow brown. It comprises a quartz
sand over most of its thickness although minor fractions of clay are found,
and occasional thin clay laminae are present. The basal layer of the Thanet
Sand is called the Bullhead Bed and is characterized by dark green rounded
flint pebbles in a silty clay matrix.
The Woolwich and Reading Beds rest unconformably on the
Thanet Sand and overstep them to the west of London to lie directly on
the Chalk. They have a similar thickness to the Thanet Sand but form a
much more varied sequence. In Docklands seven distinct facies have been
identified which reflect the variability of the environment at the time
of deposition.
After the Woolwich and Reading Beds a deep water marine
environment developed across south east England which resulted in the
deposition of the London Clay. Over its greater thickness the London Clay
is a dark grey or purplish grey fissured clay with varying proportions
of silt and some sand. On a regional scale, there is evidence that the
coarse fraction increases towards the west in the direction of the source
of sediment supply.
The formations of the solid geology are overlain by much
younger superficial materials of Quaternary age which can be separated
conveniently into the Thames Gravels and Alluvium.
The Thames Gravels form a distinctive suite of siliceous
sand and gravel which extend throughout the middle and lower Thames valley.
They were deposited during the colder phases of the Pleistocene under
braided conditions following episodic periods of high stream discharge
and can be separated into a series of local terraces.
After the last glacial period an overall rise in sea
level allowed the deposition of alluvial muds and silts with subordinate
and locally extensive peats across the present flood plain of the Thames.
This deposition has continued to the present day. In Docklands the present
distribution and condition of the alluvium has also been markedly influenced
by the effect of man in the historical past. Across much of the urbanized
parts of the flood plain the alluvium has been surcharged by made ground
placed above it, or has been partly or completely excavated.
Top of Page
Top of Chapter
Contamination
The previous use of the Urban Development Area (UDA)
means that it is potentially contaminated by chemical pollution. The effects
of such contamination are usually permanent, or at least very long lived
so that even where there is no evidence of the original cause of the contamination
the problem can be sufficiently severe to represent an immediate or long
term hazard to human health, to vegetation or construction materials.
The source of the contamination is related invariably
to human activities and can arise from a variety of causes so that the
development of most sites has not been possible without adequate reference
to the possibility of pollution being present. A detailed understanding
of the condition of this is essential if a remediation strategy which
would allow safe development could be adequately assessed or correctly
formulated.
LDDC commissioned a Register of Historic Land use from
A F Howland Associates. This had similarities to the philosophy of the
register of contaminating use then proposed under section 143 of the Environmental
Protection Act, but took the principle further in that, not only was the
presence of a contaminating use established but, the history of the site
was also recorded. This was supplemented by three other systems which
dealt with the data collected from within the area. Together these have
provided a systematic approach to the assessment and appreciation of ground
conditions able to deal with areas of even gross contamination. A number
of treatment programmes have been instigated by LDDC and it has also overseen
others by virtue of its powers as local planning authority.
The remedy which may be necessary for any situation is
related to the sensitivity of the proposed end-use. In broad terms the
options fall into one of three categories:
- removal and replacement,
- treatment, including;
~ physical (solvent leaching, flotation etc.)
~ chemical (oxidation, hydrolysis, neutralization etc.)
~ thermal (direct heating, steam stripping etc.)
~ microbial (selected microorganisms, vegetation etc.)
~ stabilization/solidification (cement or resin based
systems)
Removal and replacement is by far and away the easiest
option. It eliminates the problem in a simple and easily understood way.
It does however, suffer from the scale of works that may be necessary
to remove significant amounts of contaminated soil from any one site.
Removal and transport of the material must be strictly controlled and
it must be disposed of within current legislation. The disposal of contaminated
material can only be to a licensed site and any such disposal reduces
a finite capacity of the disposal resource.
Treatment of contaminated material has scientific elegance
but suffers in that no single system is able to deal with the full range
of contaminants which may be found on any one site. In fact the mix of
substances may affect or reduce the effectiveness otherwise achieved by
some processes. Unless a single suite or family of chemicals is present,
as may be found after contamination by a single event such as a spillage,
then a complex series of procedures may be necessary. The time required
by some of the processes can also be lengthy so that the need to protect
the site during the treatment process may be as great as if the contamination
was left in place. Finally, residual contamination on complex sites often
means that subsequent removal or containment may still be necessary.
Containment of the polluted material ensures that contact
with it, and any migration of it, is prevented. The procedure often relies
on a surface capping to provide a physical barrier between the end user
and the contaminated material. The thickness and type of barrier is determined
by the proposed end use. Where there is a concern that migration from
the site may occur a perimeter barrier can be installed. However, if migration
is likely, the principal migration pressure will result in a downward
movement and the installation of such barriers below sites with historical
industrial contamination is not possible without the initial removal of
the contaminated soil itself.
In Docklands many sites have been developed with traditional
residential housing on areas where contamination has been proved to be
present. In all cases the approach adopted has been for containment. Two
prime examples are the Winsor Park Estate in Beckton and Thames Barrier
Park, Woolwich.
Top of Page
Top of Chapter
Hydrogeology
Two aquifers have an influence on the hydrogeology of
Docklands. A lower aquifer comprises the Chalk, together with the overlying
Thanet Sand and more sandy basal units of the Woolwich and Reading Beds,
and an upper aquifer consists of the Thames Gravels. Over part of the
area these are separated by the relatively impermeable London Clay or
the cohesive units of the upper units of the Woolwich and Reading Beds,
so that the lower aquifer is confined and the conditions in the two are
unrelated. Over the remaining part of the area the Thames Gravels lie
directly on the lower aquifer such that it becomes unconfined and there
is a resulting hydraulic continuity between the two.
In a natural state the hydrogeology of the area has a
stability which is a function of both the local and regional geology.
In the historical past this natural balance has been upset by the influence
of man (Figure 2). Groundwater
abstraction in central London during the past 200 years has caused a cone
of depression up to 85m deep which spread into the Docklands area (Figure
3). By the 1960's the piezometric surface in the lower aquifer
fell from Ordnance Datum south of the Thames at Woolwich, to -8 metres
OD on a line which crossed the Royal Docks and the southern Isle of Dogs
and deepened rapidly westwards to -60 metres OD through Wapping. A general
rise in groundwater has been recorded since the major abstraction ceased.
This is also evident in the Docklands area where the piezometric surface
in the Southwark area has risen at up to 1.2 metres/yr, although this
has possibly been enhanced by leakage from the Docks system. In the east
of the Docklands area the groundwater appears to be in equilibrium with
the natural situation, although again leakage from the docks has a marked
local influence.
The hydrogeology of the area is presently in a state
of transition and will vary within the timescales of modern development.
Nonetheless, there remains a basic relationship between the various controlling
factors to allow an understanding of the overall situation.
Top of Page
Top of Chapter
Thames Barrier Site
The Thames Barrier Park forms a plot of land of 9 ha.
which lies adjacent to the River Thames. It lies in a stretch of land
along the river frontage which has had various heavy industry for about
the last 150 years. The site and immediate adjacent areas have had a variety
of industrial activities which include:
- rubber works
- telegraph works
- petroleum distillation plants
- manufacturers of treated timber, including
~ production of creosote oils and
~ other tar products
- chemical works manufacturing
~ oleum
~ sulphuric acid
~ hydrochloric acid
~ alkalis and
~ chemical fertilizers
~ "specialist" chemicals'
- Dye works
- Tar refinery producing -
~ phenols and cresols
The Ordnance Survey map of 1893 shows the intensity of
industrial activity on the site (Figure 4
- 152k) . None of these structures are present today. Some
of these were tanks and reservoirs and therefore are the likely sites
of significant infill.
Initial remediation of the site involved the removal
of mass concrete substructures and draining of buried tanks and smoothing
of the land profiles. The concrete was crushed and graded to form a protective
layer to the site while the final development layout was determined. Once
this was finalised the existing crushed concrete was stripped and further
cut and fill undertaken to form the required contours. Following removal
of any further visibly contaminated material the crushed concrete was
replaced and a capillary break layer laid above this. This was protected
by a geotextile filter before the final depth of subsoil and topsoil was
spread on top.
Top of Page
Top of Chapter
Winsor Park
Development
Beckton housed one of the largest gasworks based on coal
carbonisation in Europe. It produced gas from 1870 and finally ceased
operation in 1968 (Figure 5 - 150K)
. It also had a large chemical by-products works situated adjacent to
the main production area. The area south west of the works acted as a
marshalling yard for the storage of coal and coke. It also accumulated
large amounts of waste from the works.
A succession of investigations showed that contamination
was present over much of the area including various liquors and tarry
products. Surface water ponding on the area was also shown to be highly
acidic and contaminated with oil-tar material.
The waste products were to depths of 4 metres and included
substances which are both toxic and carcinogenic even at very low concentrations.
In addition many of the contaminants are also corrosive and therefore
damaging to construction materials.
The LDDC became involved in the site through a compulsory
purchase order. This went to public enquiry at which the LDDC argued that
the area should be developed for housing and that the contaminated nature
required a total and managed approach to the treatment of the area as
a whole. It was argued that this would optimise the resources available
and lead to a better control of the attendant operations than would otherwise
be possible if the total area was developed on a piecemeal basis.
Consideration of the whole site would also allow a greater
flexibility of approach to its reclamation. The level of contamination
classified the material as special waste under the then Control of Pollution
Act 1974. The large volumes of material involved meant that its total
removal and disposal was impractical.
Treatment of the material was largely impractical because
of the variability of material present and timescales required for the
completion of the process.
It was concluded that the only viable approach to the
reclamation of the area was by a containment system (Figure
6 - 63k). This had the advantage that no material needed
to be removed from site and the system was instantly available once the
engineering works were complete. In view of the degree of contamination
it was felt that the barrier should consist of a minimum of a metre clean
imported material.
Dr AI Howland MSc, PhD, D.I.C. C.Eng.,
FIMM CGeol FGS
A.F. Howland Associates
Note by Webmaster: For more on the work of A.F.Howland
in Docklands visit the company web site at http://www.howland.co.uk
Top of Page
Top of Chapter
Construction of the Docklands Highways
Click here for Location Plan - 182k
London Docklands is now served by the Docklands Light
Railway (DLR), a network of new four lane highways, improved roads, existing
roads including a major trunk (the east-west A13), two tunnels crossing
the Thames - the Blackwall and the Rotherhithe Tunnels - London Underground
in the west, an airport, ever improving bus services, British Rail and
construction work nearing completion on the Jubilee Line Extension, scheduled
to open in Spring 1999. 83,000 people live in the area and 85,000 work
here.
Seventeen years ago the area was served by the one main
road - the A13 - the two Thames tunnels, and a series of local roads skirting
high dock walls and, on these roads, an infrequent bus service. Local
minicabs played a major role in moving the 39,400 residents to and from
the London Transport network, mainly at Mile End tube station on the Central
and District lines. The working population was 27,200 and declining.
When the LDDC was set up in 1981 with the task of securing
the lasting physical, economic and social regeneration of the area it
was faced with large areas of land that nobody wanted to buy, no new private
investment and nothing to trigger growth. The housing was predominantly
rented, mostly by the local Councils, deteriorating and quite often considered
undesirable and, more importantly, the outdated infrastructure needed
major public investment.
It was recognised from the outset that the area could
only generate new opportunities if it was opened up and access dramatically
improved. The challenge was to achieve this by creating a public/private
sector partnership and by levering in new investment.
The Corporation was given planning control powers; powers
to buy and sell land; and an annual grant voted by Parliament. It was
not to be a housing authority, a highway authority nor an environmental
health authority. The apparent impotence imposed by the lack of these
powers, particularly in building roads, required the LDDC to liaise in
detail with the relevant boroughs and other authorities.
Top of Page
Top of Chapter
In April 1982 part of the area - on the Isle of Dogs
- was given Enterprise Zone status with all the inherent financial incentives
for developers and investors. Within two to three years low rise buildings
and light industrial workshops had been attracted. The transport needs
were to be met by a series of new and improved local roads together with
the Greater London Council's (GLC) Docklands Northern Relief Road, a good
bus network and a light rail system, the DLR, which would operate on new
and old viaducts previously used by trains servicing the docks. The decision
to build the DLR (from Tower Gateway to Island Gardens and up to Stratford)
was taken in 1982. Construction commenced in 1984 and the railway opened
to the public in 1987. Roads serving the Enterprise Zone were built by
1984 and a two lane road, parallel to and south of Poplar High Street
was completed by 1986. The latter had in fact been devised as a stage
of the Docklands Northern Relief Road by the GLC in the mid 1970s.
As late as 1984 the highest estimate for the level of
activity in the Isle of Dogs forecast a maximum of 8 million sq. ft (743,000
sq.m.) of commercial development. However, by 1986 outline approval had
been given for a single 12 million sq. ft (1.1 million sq.m.) development
on Canary Wharf in the heart of the Enterprise Zone and other large scale
proposals amounting to a proposed 40 million sq. ft (3.7 million sq.m.)
were being considered on the Isle of Dogs. The property boom of the mid
1980s and the tax advantages of the Enterprise Zone saw a fourfold increase
in the development projections for the area within a short timescale.
In the light of the enhanced development expectations,
the Corporation formed a transport strategy with the following key objectives:-
- to provide good access to the development areas from the major road
and public transport networks;
- to reduce the barrier effect of the River Thames and the River Lea
and improve links within Docklands;
- to provide an integrated public/private transport network with the
capacity sufficient to meet the proposed increased demands from new
developments, but with the emphasis on public transport;
- to improve local transport facilities and access, for existing and
new residents, to employment and leisure facilities.
An extension of the DLR to Beckton in the east was proposed,
in parallel with the extension to Bank in the west, which was to be jointly
funded by Canary Wharf developer, Olympia & York, and London Transport.
To integrate with the DLR and other public transport
modes, the Corporation initiated a strategic highways network, comprising
ten major schemes running west to east through Docklands, known as the
Docklands Highways.
For a full description of the Corporation's transport
strategy see the LDDC's publication "Starting
From Scratch".
Top of Page
Top of Chapter
Docklands Highways
The first three schemes constitute in effect a variation
on the Docklnds Northern Relief Route which was incorporated into the
Docklands Highways programme to ensure that it was built as the abolition
of the GLC in April 1986 had further placed it in jeopardy.
Proposals for the Docklands Highways were approved by the LDDC Board in
mid 1986. Just over three and a half years later most of the major schemes
were on site and all had been completed by May 1993 at a total construction
cost of some £570 million.
Top of Page
Top of Chapter
Limehouse Link
The 1.8 km four lane tunnel links The Highway, at the
junction of Butcher Row and Narrow Street, to Westferry Road and to North
Quay on the Isle of Dogs. The road passes under the north side of Limehouse
Basin, turning south to pass underneath Limekiln Dock and Dundee Wharf
and joins with Westferry Road and the Poplar link. The scheme also included
the widening of Westferry Road from Westferry Circus to West India Dock
Road. Construction started in November 1989, and the road opened in May
1993.
Contractor: Balfour Beatty AMEC Joint Venture
Consulting Engineers: Sir Alexander Gibb & Partners
Top of Page
Top of Chapter
Poplar Link (Aspen
Way)
Built in phases over two and a half years the Poplar
Link upgrades a road already built along this corridor by the Corporation.
The west side of the scheme included improvements to West India Dock Road,
along with the realignment of the junction with the A13 Commercial Road.
The 1.4km varies from a four to six lane road and its alignment continues
from West India Dock Road, eastwards across the north of the Isle of Dogs
to Prestons Road Flyover. A major new roundabout at Prestons Road links
with the East India Dock Link (Aspen Way east). The full scheme opened
in May 1993.
Contractors: Percy Bilton plc,.
Roadworks (1952) Limited,
Mowlem South-East
Consulting Engineers: Mott MacDonald
Top of Page
Top of Chapter
East India Dock Link/Prestons Road Flyover
A dual carriageway road, about 1 km long, links Prestons
Road roundabout with East India Dock Road (A13), at the Canning Town Flyover.
Developments are served by roads connected to a new roundabout at the
southern end of Leamouth Road, which in turn links to the Lower Lea Crossing.
The northern end of East India Dock Link, connecting with the A13 by a
cut and cover tunnel under East India Dock/Leamouth Road, has been upgraded
to dual carriageway, including the new junction with the A13. An east-west
flyover has been built at Prestons Road roundabout connecting East India
Dock Link with Poplar Link. Construction of the tunnel and flyover started
in November 1990, with the scheme opening to traffic in May 1993. This
scheme only completed the westbound bore whilst the eastbound is due to
be completed by the Highways Agency as part of future A13 major improvements.
Contractors: Wimpey Major Projects (Phase 1),
Edmund Nuttall Limited (Phase 2),
T E Beach Ltd (Leamouth Road)
Consulting Engineers: Mott MacDonald
Top of Page
Top of Chapter
Canary Wharf Eastern Access (Trafalgar Way)
This 750 metre dual carriageway links the roundabout
at Prestons Road to the eastern end of Canary Wharf, via the northern
and western boundaries of Poplar Dock. Two bridges span the entrance to
Blackwall Basin and across the West India Docks onto Canary Wharf. The
scheme was built between August 1989 and November 1990.
Contractor: Taylor Woodrow Construction
Consulting Engineers: Mott MacDonald
Top of Page
Top of Chapter
Lower Lea Crossing
This four lane road, approximately 1 km long, connects
the Isle of Dogs with the Royal Docks, linking the roundabout at Leamouth
Road with a new roundabout underneath Silvertown Way Viaduct. The road
includes a bridge over the River Lea. Construction started in February
1990 and the road was opened in December 1991.
Contractor: Norwest Holst Construction
Consulting Engineers: Mott MacDonald
Top of Page
Top of Chapter
Enterprise Zone Road Improvements
The distinctive red brick roads built in the Enterprise
Zone, which already carry substantial volumes of traffic, have progressively
been improved with an asphalt wearing course, new turning lanes, bus laybys
and upgraded junctions, and are being repaired after the damage done by
the Docklands bomb in February 1996.
Top of Page
Top of Chapter
North Woolwich Road
A two lane section of North Woolwich Road, south of the
Pontoon Dock, has been widened over a length of approximately 500 metres,
with landscaping on the north side to complement the established Silvertown
Tramway scheme to the south. Work started in May 1988 and was completed
in May 1990.
Contractor: Fitzpatrick & Son (Contractor) Ltd
Consulting Engineers: London Borough of Newham
Top of Page
Top of Chapter
Connaught Crossing
A new four lane north-south road, about 900 metres long,
has been built between Royal Victoria Dock and the King George V and Royal
Albert Docks. It links North Woolwich Road and Factory Road in the south,
to Connaught Road and the Royal Albert Dock Spine Road in the north, with
roundabouts at both junctions. A third roundabout links east to Connaught
Road and London City Airport and west to the Pontoon Dock area. The road
crosses the dock cutting on a swing bridge and was built in several stages,
starting August 1987. The crossing opened to traffic in February 1990.
Contractors: Norwest Holst Construction (Phase 1),
Peter Birse Ltd (Phase 2)
Consulting Engineers: Sir William Halcrow & Partners
Top of Page
Top of Chapter
Royal Albert Way
The 1.8 km Royal Albert Way is the major east west link
between the Connaught Crossing and Royal Docks Road. The dual two lane
road runs south of and parallel to Strait Road along the full length of
Royal Albert Dock. Intermediate roundabouts serve the area and, in two
cases, allow for integral stations on the DLR, Construction started in
March 1988 and the road opened in April 1990.
Contractor: Edmund Nuttall Limited
Consulting Engineers: Frank Graham & Partners
Top of Page
Top of Chapter
Royal Docks Road
This predominantly dual carriageway two lane road, about 2km long, extends
from the A13/A406 (South Woodford to Barking Relief Road) junction to
a new roundabout around the Gallions Pumping Station. An extension from
this roundabout serves the Beckton Gas Works site and the DLR depot. Work
started in June 1986 and the road opened in October 1989.
Contractors: John Laing plc (Phase 1),
Percy Bilton plc (Phase 2)
Consulting Engineers: London Borough of Newham
Top of Page
Top of Chapter
The Limehouse Link - Engineering Case Study
Location Plan - 203k
Longitudinal section of Limehouse Link showing geology
- 55k
Cross section of Tunnel and Eastern Services Building
- 48k
Base Construction - 44k
Limehouse Link is the critical link in the highways network, providing
the psychologically important direct connection to the City of London
and on to the West End. As well as improving access to the surrounding
East London strategic road network, it has brought significant traffic
relief to Limehouse which, combined with traffic management measures,
secured improved environmental conditions for local residents and future
development.
LDDC studies identified a number of options to build
the link between the Isle of Dogs and the City. The scheme built is a
two lane dual carriageway with an underground junction at Westferry Road.
The alignment at the western end is determined by the presence of the
Rotherhithe Tunnel approach ramp, from where it curves along the northern
edge of the Limehouse Basin. Here the tunnel depth is dictated by the
navigable depth required for the connection between Regent's Canal and
the Thames. From here the route runs through an open area, Ropemakers'
Fields, between existing housing; it then crosses under Limekiln Dock.
The tunnel then widens to accommodate slip roads leading to and from Westferry
Road and Canary Wharf. It continues under the DLR and West India Dock
Road before rising to the surface to connect with the Poplar Link. The
total length is 1.8 km, with 1.5 km in tunnel; the roof is generally 6
- 8 metres below ground.
Planning permission for the road was granted in July
1988 after the Secretary of State for the Environment decided not to call
in the planning application. A public inquiry into the Compulsory Purchase
Order, needed to acquire necessary land which the LDDC had not been able
to obtain by agreement, was held in October 1989 and lasted four weeks.
Top of Page
Top of Chapter
The Accord
The co-operation of Tower Hamlets, as housing authority
and highway authority for the area, was essential, and after lengthy negotiations
the LDDC signed an Accord with the Borough Council in an effort to minimize
disruption for people living along the line of the road. In return for
the Council's co-operation and support for the Docklands Highways schemes,
the LDDC undertook to provide replacement housing and to refurbish existing
accommodation for those tenants directly affected. The LDDC paid for 301
homes to be refurbished, 556 households were moved to new housing association
homes or refurbished council flats; and secondary glazing was provided
in 338 homes to alleviate noise during construction. In addition, the
LDDC provided a £35 million package of social, economic and community
developments to benefit residents of Tower Hamlets.
Top of Page
Top of Chapter
Design of the Link
Consultant, Sir Alexander Gibb & Partners, was appointed
by the LDDC in 1987 with a brief to confirm the route alignment, to determine
the scope of the site investigations needed, to identify construction
methods to minimize environmental impact, to design the structure and
services and to prepare tender documentation. This was to be done to a
fast-track programme allowing less than two years to tender stage. The
tunnel box was to be designed to carry loads resulting from future development
overhead.
There was no precedent for construction of this type
of tunnel in the variable ground conditions of East London. Design began
with an information gathering exercise to collect published data on ground
conditions, and to find historical information on earlier construction
in the area. Construction records could not be found for many structures
alongside the road, so structural surveys were carried out on buildings
and structures within 40 metres of the tunnel. Risby House, a Ronan Point
type residential tower block, was found to be in a critical condition
already. The tenants were rehoused under the Accord and it was demolished.
Ground conditions were complex with made ground overlying
Thames Gravel, London Clay, Woolwich and Reading Beds, Thanet Sands, and
chalk bedrock. Structural design of the tunnel was dictated by the difficult
water-bearing strata. Geotechnical investigations were delayed by access
problems, so the initial design was carried out to provisional parameters.
The investigation subdivided the Woolwich and Reading Beds into five sub
layers with differing properties. When final results became available
in August 1988, the design parameters turned out to be more conservative
than had been assumed, requiring extensive redesign of the tunnel walls
during the tender period and initial construction period.
The design adopted a plain rectangular tunnel box for
ease of construction, with twin bores 10 metres wide separated by a central
wall. A width of up to 22 metres was needed to accommodate the slip roads
for the underground junction. The box was 7.8 metres high, providing clearance
for services overhead and depth for service trenches below the road surface
level. Connections between the external walls and roof and floor slabs
were pin jointed with dowels for temporary support of the slabs during
construction. These were to be supplemented by skin (shear) walls constructed
inside the tunnel box after casting of the base slab. Computers were used
extensively in the structural design.
The tunnel has a design speed of 60 km/h, with a medium
centreline radius of 189 metres and gradients on the approach ramps of
up to 6.8%. Development surcharge load was fixed at 80 kN/sq.mtetre, equivalent
to a four-storey building.
Ground conditions and the relatively shallow tunnel depth
dictated that construction should be by cut and cover methods. In order
to minimize the construction corridor width and ground movements, 'top
down' construction was specified.
Top of Page
Top of Chapter
Envisaged construction sequence
Diaphragm walls would be built on each side of the tunnel,
to 4 metres below base slab level, to form the external walls of the tunnel
box.
Excavation would be carried out down to roof soffit level,
and the diaphragm wall upstands would be propped where excavation exceeded
3 metres. The roof slab would then be cast.
Excavation under the roof slab could then continue through
openings left for this purpose. Props would be installed at mid-bore before
excavation continued to slab soffit level. The slab would be cast and
the box would be completed by casting the central and shear walls. Finally,
backfilling to the original ground level would be completed over the roof
slab.
Top of Page
Top of Chapter
Services
The tunnel required a wide range of services, including
11 kV electrics, closed-circuit television, traffic management, radio
communications and variable message road signs. Services are controlled
by a computerized system linked to the operations control room and the
Metropolitan Police Control at East London Traffic Control Centre.
Ventilation extract fans, power distribution and other
services are housed in three service buildings framed in reinforced concrete,
housed over the tunnel portals and a fourth off-line building east of
the Limehouse Basin.
Design of the ventilation system was complex because
of the varying width of the tunnel bores and the slip roads located part
way along. The design requirement was to keep concentrations of carbon
monoxide and diesel smoke within acceptable limits under all operating
conditions. In addition, a minimum air flow speed of 4 metres per second
was required to be generated for emergency control of smoke and heat.
A longitudinal ventilation system with jet fans mounted along the roof
soffit was adopted to propel air in the direction of traffic flow. Computer
modelling took into account factors such as external wind speeds of up
to 3.5 metres per second.
At each portal, axial fans extract air from beneath the
tunnel roof and discharge it through high level vent stacks. The system
is controlled automatically by carbon monoxide analysers and visibility
monitors.
Top of Page
Top of Chapter
The
Contract and Alternative Design for the Limehouse Basin
Civil and electrical/mechanical works were let as a single
contract because of the complexity of interfaces between them. Because
of the complexity of the project a critical path analysis of 400 significant
activities was carried out to determine a 48 month construction period.
The form of contract used by the LDDC was the Property Services Agency's
GC Works 1 amended to include a clause on unforeseeable ground conditions
with Sir Alexander Gibb & Partners as superintending officer. Tenderers
were invited to submit alternative designs.
A joint venture of Balfour Beatty and AMEC submitted
a proposal to build the section through the Limehouse Basin bottom-up
within a cofferdam, rather than top-down. This offered a £4 million saving
and, more importantly, a six month reduction in the contract period. This
alternative could only be used in the Limehouse Basin area because of
the proximity elsewhere of residential properties and the noise and vibration
of cofferdam installation. The tenderer was able to satisfy concerns about
ground movement, particularly adjacent to the DLR viaduct, and the Balfour
Beatty AMEC Joint Venture was awarded the contract in October 1989 and
construction commenced in November 1989.
Robert Benaim & Associates were commissioned by the
joint venture to design the permanent works for the alternative section
and this was checked by Sir Alexander Gibb & Partners. The contractor
designed temporary works in house and these were checked by Benaim. Close
co-operation between the joint venture and Benaim allowed further modifications
to the design of the tunnel box, giving cost. and programme benefits and
improved buildability. These prompted many of the alternatives proposed
when value engineering was introduced later in the contract. Among these,
the base slab was designed to incorporate the road construction make up,
main surface water drainage and four service trenches.
Top of Page
Top of Chapter
Environmental Constraints
During construction, noise and vibration levels were
limited under a Section 61 of the Control of Pollution Act 1974 by an
agreement negotiated with the London Borough of Tower Hamlets by the LDDC.
Some properties had to be temporarily vacated. Because of the proximity
of residential areas, most construction activities were restricted to
between 8 am and 6 pm. However, some work was allowed to continue on a
24 hour profile with the obvious imposition of a lower noise limit during
the night. For environmental reasons, and to minimize traffic congestion,
most materials and equipment were delivered and removed by river, via
a specially built 200 metres long temporary wharf at Dundee Wharf. This
handled 3.5 x 106 tonnes of materials and spoil during the contract.
Top of Page
Top of Chapter
Concrete delivery
Of the 310,000 square metres of concrete used in the
project, 78% was mixed by computer -controlled hatching plant, with a
combined capacity of 195 cu m/h at Dundee Wharf. Most concrete was pumped
directly from the plant to each pour through 125 mm pipes. Single pump
distances of 700 metres were achieved, and stage pumping increased this
to over 1,000 metres at rates of 50 cu m/h.
Top of Page
Top of Chapter
Contract Variations and Value Engineering
The contract underwent considerable changes, not least
the late access to areas on the site and delayed installation of secondary
glazing to adjacent residential properties. These held up progress, which
led to a variation agreement between the Joint Venture and the LDDC to
mitigate the effects. Later, a contract amendment incorporated further
variations. These brought about several changes, including additional
tunnel work fronts and resources, a review and resolution of delays at
90-day intervals, a lump sum fixed price for the works, and the LDDC assuming
the role of superintending officer to bring the client and contractor
closer together, with Sir Alexander Gibb & Partners remaining as resident
engineer. The most important change, however, was the introduction of
value engineering.
Value engineering was introduced in March 1991 by the variation agreement.
It enabled the joint venture to propose changes to the design and to benefit
from a share of any savings. This allowed delays to be recovered, and
overall completion was achieved five-and a-half months early, affording
substantial financial savings for both the contractor and the client.
Value engineering proposals were developed by the Joint Venture with its
consultants, Robert Benaim & Associates and Mott MacDonald. Of 13
major proposals made, nine were accepted. - The following were the main
ones:
The very heavy reinforcement content of
the roof slab was reduced by shaping it to complement the maximum stresses
developed in it. In addition, the road construction make-up and drainage
were incorporated into the structural base slab, instead of being added
afterwards, removing a major secondary activity from the construction
programme.
The continuous internal skin wall was
replaced by a series of skin columns performing the same structural function
but with a 60% reduction in materials.
-
Temporary roof slab support:
Modifications to the base slab design
and temporary roof slab support allowed the central wall to be built in
bays three times longer than originally detailed.
-
Eastern services building ground floor support slab:
An additional row of central columns enabled
a 2.5 metres deep 22 metres span in-situ slab to be replaced by two 1
1 metres span composite precast beam in-situ 1.2 metres deep, saving 60%
in materials.
-
The observational method:
Apart from the redesign of the base slab,
this was the most significant of the value engineering changes in terms
of savings in cost and time. Developed in association with Mott MacDonald,
it allowed tunnel props to be omitted. Key factors in the success of the
observational method were speed of construction (to take advantage of
the short-term strength of the soil), the accuracy and reliability of
measurements, and the availability of contingency plans to react to unacceptable
events
The original design required temporary propping - by
1340 mm diameter steel tubes at 4.2 metre centres - of the side walls
during top-down construction. Props were to be installed above and below
the tunnel roof slab and loads in them monitored. As well as hampering
excavation below prop level and slowing construction, the original design
would have required handling 6450 tonne of temporary steelwork. The observational
method allowed this to be reduced to 1550 tonne. However, monitoring of
the props above slab level showed that loads were much lower than expected.
Top of Page
Top of Chapter
The method was applied in stages. First, the props were
installed and loads monitored as excavation progressed below them. They
were found to be typically only 10% of design load. The next stage was
to change to 'soft props' with a predetermined gap at one end, while monitoring
wall convergence. Provided this was within acceptable limits, construction
could proceed without props. A number of reserve props were kept near
each construction front as a contingency against unacceptable movements.
A maximum total wall convergence of 70 mm was allowed
at slab soffit level. The maximum observed movement was 11 mm, and convergence
was generally less than 7 mm. The method was applied to all nine construction
fronts in the top-down sections of construction and in all cases props
were successfully dispensed with after going through the initial stages
of using first 'hard' and then 'soft' props. Although difficult to quantify,
elimination of the difficulties of handling and working around the vast
quantities of steelwork made the observational method safer than the original
design.
Value engineering gave rise to major savings in material
and contributed greatly to the recovery of earlier delays. But the Limehouse
Link's greatest success was due to the close co operation between the
client, contractor, and all the design teams involved. Without this, many
of the innovations and engineering achievements would not have been realized.
Top of Page
Top of Chapter
Running the Roads
With the opening of the Limehouse Link and the rest of
the Docklands Highways on 17th May 1993, the LDDC was responsible for
managing and operating the 32 km (17 miles) of road, 22 km (12 miles)
of which could be classified as major carriageway. This is thought to
be the largest privately owned road network in Europe which is accessible
to the public.
The LDDC decided to retainresponsibility for the operation
of the roads, which would normally have been done by a highway authority,
as it wanted to take a proactive role in minimising disruption for residents
and incoming companies and to ensure that traffic was kept moving safely
and efficiently while developers were constructing the major schemes in
the area.
Top of Page
Top of Chapter
Controlling Forces
Traffic control can be carried out in a variety of ways,
but the LDDC team found that personal contact is the answer even in an
area synonymous with high-tech developments.
From the legislative point of view, the Highways Act
does not strictly apply to LDDC's roads, although for practical purposes
the Corporation acts as a traffic authority not as a highway authority.
The Road Traffic Act does however apply, and the provisions of Chapter
8 are administered, along with traffic management in the joint names of
the LDDC and the relevant highway authority orders for speed and clearways.
The LDDC operations team consisted of up to 50 people,
half of which worked on managing the operation and maintenance of the
Limehouse Link and the East India Dock Tunnel, and the others on the remaining
highway network including road safety officers or 'white-caps' who constantly
patrol the area dealing with minor incidents such as illegally parked
vehicles, giving directions and information, manning shuttle working,
laying out traffic management equipment, keeping an eye out for areas
or items which require maintenance and assisting at accidents and incidents.
The team is based in a purpose built building in Orchard Place from where
the tunnel is 'driven'.
The accident rate in Docklands is lower than average
for the length and type of road but probably greater in variety. There
were incidents however, such as the horse which had escaped from the City
Farm and was determinedly trotting the wrong way round a roundabout, and
a rather less savoury escapade when a jack knifed lorry from a local food
processor spilt 30 tons of pigs heads across a dual carriageway.
Procedure for these incidents is fixed and straightforward.
All the team members are routinely equipped with safety equipment and
five channel two-way radios. The moment an incident is reported it is
recorded. Information is recorded on a real time database and the report
is generally started there and then. The LDDC team does not confine its
services to accidents within its own area though. It has excellent relationships
with opposite numbers in the Metropolitan Police, Tower Hamlets, Newham
and Southwark and routinely offers assistance if appropriate.
The simple aim had to be to keep the traffic moving which,
all things considered, was achieved very successfully with a programme
of information and strict enforcement, including the production of a newsletter
entitled "Keep The Traffic Moving". This showed drivers where
the construction activities and possible delays were.
CCTV cameras cover the approaches to the tunnel and the
tunnel itself with sensors in the road surface to measure traffic flow,
speed and congestion.
The Limehouse Link is closed regularly for routine maintenance
by the team at night, whereas the East India Dock Tunnel is cleaned with
lane closures only.
Top of Page
Top of Chapter
Considerate Contractor Scheme
With help from the City of London engineers, the Corporation
instigated a 'Considerate Contractor' scheme. The construction sites were
patrolled by two former police officers, as part of the traffic control
team and ensured that the interface between the public and the contractor
was safe and clean. Given the amount of construction which took place
during the late eighties and early nineties, they proved remarkably effective.
Top of Page
Top of Chapter
The Future
The Docklands highway network covered the three Docklands boroughs Newham,
Southwark and Tower Hamlets. The boroughs have or are in the process of
adopting all the LDDC's roads and the Corporation has progressively handed
on its responsibilities in the area since the end of 1994. The exceptions
are the Limehouse Link and East India Dock Link tunnels and the connecting
dual carriageway, Aspen Way and Prestons Road Flyover, whose ownership
will transfer to the Commission for the New Towns, the government agency
which takes on all remaining assets and liabilities of the English Urban
Development Corporations, including LDDC, from 31st March 1998.
Bob Blyth BSc, C.Eng., M.I.C.E., M.I.N.T.
Partner, W.A. Fairhurst & Partners
(formerly LDDC Chief Engineer)
Top of Page
Top of Chapter
River and Dock Walls
River Walls
The LDDC, at its peak, owned some 13 km of river walls
from Tower Bridge in the west to Gallions Reach in the east. LDDC found
it was responsible for maintaining an effective flood defence at all times,
as required under the Thames River (Prevention of Flood) Act 1879, the
Land Drainage Bylaws 1981 and the Water Resources Act 1991. The flood
level upstream of the Thames barrier is 5.23 metres Ordnance Datum Newlyn
(O.D.N.) and 7.2 metres O.D.N. on the downstream side of the Thames Barrier.
The types of the various walls that the LDDC inherited
as owners of the adjacent land were varied. They ranged from war damaged
and emergency repaired brick walls in the upper pool of London in Wapping
to almost non-existent timber walls at Galllions Reach. The walls varied
in construction from the earlier mass concrete gravity walls to the relatively
modern sheet-piled walls frequently with high level ground anchor supports.
When it became necessary to check the stability of old
walls with high level tie-backs or anchors, site inspection often found
either the old mild steel anchor rods in very poor condition or in some
cases, a minimalistic sign of the original anchor rod was indicated only
by rust staining of the soil. Similarly, original timber anchors were
sometimes found to have rotten away almost completely. Naturally, this
was of great concern to the inspecting civil engineers as these walls
were calculated to be instable and required remedial action.
The reason for these material failures could have been
either poor original materials or aggressive ground conditions, as the
areas adjacent to the river have historically been used for industrial
purposes and were frequently contaminated. These contaminants could have
attacked the walls and their associated ground anchors. As a consequence,
modern rebuilt walls use quality materials with protective coatings. Sheet-pile
walls were designed for a safe life-span of 60 - 70 years as required
then by the National Rivers Authority (NRA) and more recently the Environment
Agency. To achieve these life-spans, the sheet piles were protected with
epoxy-coatings applied at the factories, the anchors were surrounded in
cement grout or anchor ties were wrapped in dense tape. These protective
coatings were designed to extend the life expectancy of component parts
of the walls.
During the 17 year life of the LDDC, the Corporation
rebuilt many walls predominantly to allow development of the adjoining
land such as the residential estates at Maconochies Wharf, Caledonian
Wharf and Duggan's Wharf on the Isle of Dogs. Frequently, the new walls
were constructed of sheet-piling, some with brick wall facing, many with
concrete copings to take the hand railings. All new walls were fitted
with timber rendering to prevent damage to the walls by shipping. Figure
1 (102k) shows the walls repaired or built during the LDDC's
life at a cost of £12 million.
A major policy that the LDDC pursued whenever it developed
land adjacent to the river was to provide a public walkway, thereby allowing
people to once again enjoy the benefits of access along the riverside.
This has proved to be both environmentally enhancing and particularly
popular with the public, who can now walk for miles around the Isle of
Dogs and along the river edge in Southwark.
Top of Page
Top of Chapter
At the time of the transfer of responsibility from the
NRA to the Environment Agency, the LDDC encountered a distinct change
in policy on embanking into the river. The Environment Agency's policy
now is to not allow encroachment or embankment into the River Thames,
which has historically been carried out for centuries. The Environment
Agency believes the river is narrow enough and is concerned about the
effect of water velocity increases on the breeding beds of fish in the
water. This proved particular challenging to the LDDC when trying to repair
river walls by the tried and trusted method of driving sheet-piles on
the water side of the old river walls. Furthermore, the Environment Agency's
policy changed in 1997 away from traditional sheet-pile walls to the much
more environmentally friendly method of sloping banks or timber walls
and the like, which will promote the growth of the Thames flora and fauna.
This was particularly challenging to the LDDC's civil engineers who still
managed to design and construct walls with enhanced environmental designs.
At Gallions Reach, the new river wall was designed to accommodate the
natural growth of the salt marsh, which appears to grow only at this location
and level. Parts of the new wall were built at the same level as the old
collapsed timber wall, on which the salt marsh was growing in the naturally
deposited river silt. The wall then slopes up to the normal levels in
front of the existing flood defence wall. Both the Environment Agency
and the Ministry of Agriculture and Fisheries complimented the LDDC and
its consultants, MLM Consulting Engineers, on this design.
In the latter years of its life, the LDDC implemented
a major review of the conditions of its river walls, ready to pass the
walls onto new owners. The first phase was the repair of river walls at
Arnhem Wharf, Isle of Dogs and East India Dock entrance by Costains and
Hermitage river wall, Wapping, by Mowlem Marine at a total cost of £1.89
million.
The second phase entailed new walls and repairs at Blackwall
Goods Yard, River Lea by John Martin Construction and Gallions Reach new
walls by Jackson Civil Engineers at a total cost of £1.8 million.
The first two phases were the repair or building of new
walls because the existing were at the end of their useful life.
The third phase of the river wall contracts was a general
contract to repair defects in the remaining LDDC walls. The work was carried
out by Tilbury Douglas Construction on 23 different locations at a total
cost of £4.0 million using a prime cost contract to allow the unforeseen
element of this type of work. This contract proved to be ideally suited
to this project with a rapid agreement of the final account as a consequence.
All the LDDC walls were passed on to new owners, knowing
they will not need any further work for at least another 25 years.
Top of Page
Top of Chapter
Dock Walls
In its lifetime, the LDDC inherited and acquired six
dock systems: London Docks in Wapping, Surrey Docks in Southwark, West
India and Millwall Docks on the Isle of Dogs, East India Dock and Basin
in Leamouth and the Royal Docks in Newham.
Historically, construction of the docks started in 1763
with the Greenland Dock in Surrey Docks, Southwark and construction continued
through the years until the King George V Dock was built in 1921. As the
docks have been built over one and a half centuries, the style and type
of dock wall has varied through the years culminating in 39 different
types of dock walls. The Royal Docks in the east, which are the largest
docks, have 28 types of walls. The Royal Docks, unlike the other docks,
have been artificially raised in height from the surrounding ground by
using the excavated material on the surround of the docks back about 61
metres. Therefore, the impounded water level of 4.24 metres is over 2
metres higher than the centre of Silvertown which is located between the
river and the docks.
One of the Corporation's first projects in 1982 was the
continuation of London Borough of Tower Hamlets partial filling of Western
Dock in readiness for the construction of housing. This is part of the
former London Docks. During the early phase of the project, hundreds of
old clay pipes, together with oyster shells were uncovered at the back
of the dock walls. These were attributed to the Napoleonic prisoners of
war who were used to dig out the docks at the time of original construction
in 1805. The London Docks had a monopoly on rice, tobacco, wine and spirits
whereas the West India Docks, opening in 1802, had a 21 year monopoly
on Caribbean trade for cargoes including sugar, rum, coffee and mahogany.
The West India Docks had room for 600 sailing ships. The East India Docks
were opened in 1806 where tea, spices, precious metals, silk and porcelain
were unloaded. South of the river, the Surrey Docks opened between 1807
and 1811 to handle timber from Scandinavia and the Baltic Ports.
In the late 19th and early 20th century, longer and deeper
docks were built to meet the demands of the empire trade, i.e. Royal Victoria
Dock (1855), Millwall Docks (1868), the Royal Albert Dock (1880) and lastly
King George V Dock (1921) where great liners berthed.
Top of Page
Top of Chapter
During the blitz of the second World War, London Docklands
became the most heavily bombed civilian target in Britain. This made extensive
modernisation and rebuilding imperative in the 1950s and 60s when some
of the docks were repaired generally on an ad hoc basis. In the Royal
Docks, the LDDC was responsible for some 16 km of dock walls which artificially
held the dock water at a level higher than the surrounding areas. It was
therefore paramount that the Corporation's engineers were aware of the
structural stability of these numerous types of wall within the Royal
Docks. Surveys were carried out to investigate the types and stability
of the walls together with estimates of their useful life.
On the north side of the Royal Albert Dock and the Royal
Victoria Dock, great lengths of the dock walls were overhung by false
quays. Detailed surveys of these false quays were also carried out and
estimated costs of the repairs were prepared, which in some cases were
handed on to respective developers as a liability, which should be considered
in their business plans. As an aid to regeneration in the late 1980s,
most of the structural concrete of the suspended quay on the north side
of the Royal Albert Dock was repaired by the Corporation. Western Gateway
on the northwest edge of Victoria Dock was also rebuilt together with
associated landscaping. Parts of Pontoon Dock which were particularly
decrepit and unstable were replaced with new sheet-pile walls. The LDDC
engineers concluded that if, by some accident, the water was allowed to
drain out of the Royal Docks, approximately one-third of the dock walls
would suffer some sort of collapse or movement which would cost millions
to repair. When the new lock gates were fitted in the King George V Dock,
the only access to the Royal Docks, fail-safe systems were put into place
so that the docks can never be drained. On very high tide when there are
run-ins from the Thames into the docks, it is the policy of the Royal
Docks Management Authority (RODMA) to have water wardens on standby to
make sure that the gates close properly when the river water recedes.
This is paramount for the integrity of the Royal Docks, West India and
Millwall Docks.
Gavin Ridding BSc, C.Eng., M.I.C.E.
LDDC Senior Engineer
Top of Page
Top of Chapter
London Docklands Water Quality
The LDDC area covers 1,700 ha. of which more than 170
ha. are water. It has over 90 km of water frontage, most of which is seen
as a positive asset in regeneration of the area. The size and type of
water spaces range from small basins to the three huge Royal Docks, the
longest 2.4 km long. Several are linked by canals and locks, whereas others
are now isolated, and access to the river is limited. The principal water
areas are show in Figure 1 (52K)
and Table 1 indicates average
depths, areas and volumes of the dock systems.
Against the prevailing economic advice and opinion of
the time, the LDDC made the important visionary decision to retain the
remaining water areas, thereby adding almost 10% of open space to the
area. In the years preceding 1981, several of the docks were filled in
the belief that the newly created land was of more value than the water.
Yet it is the water which today makes Docklands such an exceptional place.
The water space is being integrated with the developments while the best
of the dock buildings and infrastructure are being brought into new, different
and active use.
The requirement of the dock waters in their former use
was basically to support shipping activity. The movement of the vessels
and the frequent locking and impounding operations meant that the water
was kept moving and had a relatively low residence time in the docks.
The waters are now 'open spaces' within the UDA and as
such, in addition to their aesthetic contribution to the area, are used
for a wide range of sports and leisure activities. Those which take place
on a regular basis include sailing, windsurfing, canoeing, rowing, angling,
sub aqua, dragonboat racing, water-skiing, wet biking and jet skiing.
In addition there is a marina at South Dock in the Surrey
Docks with 371 berths, and elsewhere in the docks mooring for historic
vessels and visiting craft. Also the large locks at the eastern ends of
the Royal Docks and the West India Docks and Millwall Docks have been
maintained in order that large ships can still enter these systems. Indeed
construction materials and spoil for the construction of the huge Canary
Wharf development has been via the docks system in the West India Docks.
The King George V Lock in the Royal Docks has an overall
length of 300 metres and can handle vessels 244 metres long by 30 metres
beam, with a draught of 14 metres on mean high water springs.
This wide range of new activity in the docks called for
a review of the use of management of the water space in the UDA. Prompted
by this, and a few early problems in maintaining an acceptable level of
water quality in some areas, the Corporation initiated a Water Quality
Study.
In 1987 two algal blooms occurred in the Royal Docks,
first of brown algae in late May - early June and then of blue green algae
in July.
These algae caused skin irritations and it became necessary
to cancel some water contact activities in the docks during these periods
of blooms. They also raised the issue locally of long-term water quality
in the docks.
The Estates Department of the Corporation had been undertaking
quarterly sampling in the docks system to check the water against microbiological
and chemical/physiochemical parameters laid down in the European Commission
(EC) Bathing Water Directive. Although this work gave some indication
of the state of the water, it was too limited to allow the Corporation
to take a pro-active role in predicting and controlling changes in the
water quality.
Top of Page
Top of Chapter
The LDDC implemented a study to assess the existing water
quality and provide long term treatment and management strategies to ensure
certain minimum standards were maintained. The study would also identify
and evaluate emergency treatment systems which may prevent the sudden
deterioration of water quality within a dock system. The brief included
an option to evaluate the effect of water quality on developer's proposals
to alter the geometry and depths of docks or to alter their water movement
regimes. The principal objectives were to provide:-
- Water of the quality acceptable for use in water contact recreational
activities.
- Water which is aesthetically pleasing at all times.
- Water which is free from noticeable odour, visible algal scum and
contaminants.
The scope of the study was:
-
Identification of relevant legislation and standards
and an assessment of the water quality targets which should be achieved,
bearing in mind the end use of each particular dock system.
-
Identification and assessment of inputs and outputs
from each dock system.
-
Assessment, evaluation and monitoring of water
quality and water movement within each dock system, both currently
and on a regular basis in the future.
-
Identification and evaluation of emergency treatment
options for each dock system with recommendations for early warning,
monitoring and implementation.
-
Development of a long term treatment and management
strategy.
A review of th |